Today, a tour of the JU Secondary School of Agriculture, Food, Veterinary and Service Activities in Sarajevo was conducted and it was determined that the contractor had seriously accepted the criticism that the works were progressing more slowly than it had been foreseen by the dynamic plan, and increased the number of craftsmen and accelerated the execution of works on processing and painting the final cornice, which resulted in the removal of the scaffolding from the third floor. The contractor also set up scaffolding on the fourth facade facing the Miljacka river and started with all the preliminary work of plastering and removing the damaged plaster.
It was decided that the stone plinth with three facades on the building should not be changed because it was in good condition and that it only needed to be sandblasted, which unfortunately had not been included as an item in the estimate of works.