– Expert supervision of the “Turbe u Prača” facility at the invitation of the contractor and investor: a full-day tour of the construction site, checking materials on the construction site; determining the installation technology and developing details of water drainage, masonry, and the foundation of the boundary wall in agreement with the contractor;
– Preparation of an expert opinion for placing an advertisement on the facility at Telali Street 17a;
– Analysis and expert opinions at the request of the Stari Grad Municipality for placing an ATM on the facility at Sarači Street 50;
– Granting approval for the rehabilitation of the boundary wall on the facility at Kranjčevića Street 22, on which the Institute conducted expert supervision;
– At the request of the tenants, the Federal Inspection was contacted regarding the works on the facility at Maršala Tita Street 21 in Sarajevo;