On 7 September 2026, a working meeting was held at which current issues relating to the execution of restoration and conservation works on the “Zgrada Zemaljske vlade II” building and the further implementation of Activities on the northern and western façades were discussed.
During the meeting, it was noted that painting of the northern façade had been completed, after which the scaffolding was removed from the said façade. The works carried out were inspected, and it was noted that they had been implemented in accordance with the previously agreed conservation guidelines and professional standards.
An entrance portal to the passageway was installed on the northern façade, thereby implementing one of the planned elements of the façade’s finishing treatment
The meeting also addressed issues relating to the method of restoring the original railings with balustrades on the western façade, which had subsequently been bricked up. Possible methods of their construction and restoration were discussed, and it was agreed that the restoration contractor would submit an offer for carrying out the works in question, after which the Institute for the Protection of Monuments would provide its final opinion on the proposed method of execution.
The further schedule for carrying out the works on the western façade was also discussed at the meeting, with the removal of the scaffolding from the third floor of the western façade planned for this week, following completion of the planned works on that part of the building.
It was noted that the restoration and conservation works were progressing according to plan and were being carried out without significant difficulties, in accordance with the project documentation, conservation guidelines and professional standards.