An assessment of the progress of the works revealed that conservation and restoration efforts have continued, specifically the removal of lime coatings down to the oldest layer on all interior walls (flat wall surfaces, the dome, arches, and pendentives) and on interior elements (the mihrab, mahfil, and minbar), as well as the removal of existing mortar joints on the exterior walls.
It was agreed that, following the injection of the walls at pre-designated locations, the works would be suspended due to low temperatures (mid-December) and resumed in the spring. During this suspension, work will be carried out on a project for the decorative painting of the interior wall surfaces, based on findings from the exploratory work.
It was concluded that the works are being executed in accordance with the project documentation and the established work schedule.