As part of its regular activities, the Institute carried out a number of administrative procedures:
- Request for an expert opinion on the submitted Current Maintenance Report for the Stari Grad Tešanj site;
- Request for approval of the current maintenance and rehabilitation project for the southern and western façades, including colour treatment, of the mixed residential and commercial building located at the corner of Maršala Tita Street and Drage Palavestre Street in Mostar;
- Request submitted by Neimari d.o.o. Sarajevo for an expert opinion on the proposed decorative motifs for the interior surfaces of the Turbe of Semiz Ali Pasha in Prača, presented through three proposed sketches;
- Request from the Central Bank for instructions regarding the treatment of the stone plinth as part of the reconstruction of the exterior façade of the Central Office building of the Central Bank of Bosnia and Herzegovina (CBBH), located at 25 Maršala Tita Street, Sarajevo;
- Request concerning current maintenance works involving the painting of the façade of the building at 21 Ferhadija Street, Sarajevo;
- Request for an expert opinion regarding current maintenance works on the National Monument “Saburina House” in Sarajevo;
- Request for approval of the current maintenance project for the front wall (čatma) of the Podgradska Mosque, Phase I – Investigative Works Programme;
- Request for approval of the conceptual design for the traffic and architectural arrangement of the plaza adjacent to the City Hall in Brodac Street, Sarajevo;
- Request for approval of the Analysis for the Rehabilitation of the Façade of the building at 1 Jelića Street, Sarajevo;
- Expert opinion issued regarding the thermal insulation and façade treatment of the building at 12 Šenoina Street, upon the request of Sarajevostan d.o.o.;
- Request for approval for the installation of an advertising sign at 14a Maršala Tita Street;
- Request for the installation of advertising signs on the building at 19 Maršala Tita Street (BBI Bank);
- Request for approval of roof replacement works on the buildings at 26 and 28 Ibrahima Trebinjca Street;
- Opinion and guidelines issued for the thermal insulation of façades on the buildings at 51 Višnjik Street and Alekse Šantića Street, upon the request of the maintenance company HETING d.o.o.;
- Official correspondence submitted to the competent Federal Inspection Authority regarding works carried out on the buildings in Oprkanj Street (Hotel Orijent) and Bakije Sokak (demolition of a wall of the Vratnik Old Town);
- Supplementary expert opinion provided following a site inspection concerning roof rehabilitation works on the Obala Gymnasium.
- As part of its regular activities, the Institute also held a series of meetings with representatives of the Kakanj Islamic Community Council regarding works on the mosque in Kraljeva Sutjeska.
- Continuous professional supervision was carried out on works at the Turbe in Prača, where preparatory activities for the interior decorative painting are currently underway.
- During the reporting period, professional supervision was also continuously conducted at the building of the National Bank of Bosnia and Herzegovina over the following works:
- Façade rehabilitation, attended by representatives of the contractor ITC Zenica, the supervising authority, representatives of the design company Urbing Sarajevo, and responsible officials of the Bank. Upon completion of the works, a preliminary acceptance inspection was carried out, resulting in several remarks which the contractor undertook to address within the agreed timeframe set by the supervising authority.
- Rehabilitation and restoration of the exterior joinery, attended by representatives of the contractor Kepler d.o.o., the supervising authority, representatives of the design company Urbing Sarajevo, and responsible officials of the Bank. Following a series of expert consultations regarding the methodology for the preparation, repair, and final finishing of the oak exterior joinery, the works continue in accordance with the contractual documentation, technical specifications, requirements and regulations of the Heritage Protection Service, requirements of the client and supervising authority, manufacturers’ instructions for the materials used, and occupational safety regulations.
- Rehabilitation of the toilet facilities on the third floor of the building. These works are currently in the preparatory phase, including the removal of existing ceramic finishes and the dismantling of worn-out installations.
October is a month of intensive work on the Institute’s journal, Our Heritage (Naše starine). Activities currently underway include the selection, review, peer assessment, and copy-editing of submitted papers. To date, all activities are progressing according to plan.