Institute for the Protection of Monuments: Facade repair works on the Church of the Assumption of the Blessed Virgin Mary in Stup

Based on the expert opinion of the Institute for the Protection of Monuments No. 7-36-4-3823-2/24 A.A, dated 5 August 2024, and the signed Contract No. 04-01/25 dated 6 January 2025 between the Investor, the Parish of the “Assumption of the Blessed Virgin Mary”, Stup, Ilidža, and the works contractor, Neimari d.o.o. from Sarajevo, for the execution of construction and craft works on the repair of the facade and the interior of the church.

The works commenced on 13 January 2025 under the conservation supervision of the expert team of the Institute for the Protection of Monuments, Azer Aličić and Dženana Šaran.

All damage to the facade was caused by poor connections between the horizontal and vertical gutters. Upon commencement of the works, the contractor immediately proceeded with erecting the scaffolding and removing the damaged layers of the facade. All damaged wall surfaces were cleaned and washed, and then replastered using all the necessary layers and techniques.

Favourable weather conditions are conducive to the works proceeding according to the planned schedule.

During an inspection of the construction site, and under expert supervision, the materials for the final treatment of the facade, up to and including painting, were defined.

By the next inspection, the contractor is required to prepare colour samples for painting the facade.