  24. 9. 2025.  Branilaca Sarajeva No. 2, Sarajevo  

The Institute for the Protection of Monuments was contacted by the Spatial Planning and Investment Service of the Municipality of Centar Sarajevo with a request for the issue of approval for the installation of an illuminated advertisement on the façade of a residential and commercial building at 20 Branilaca Sarajeva Street.

Upon reviewing the submitted documentation and conducting an on-site inspection, it was established that the building in question falls within the area of the national monument of BiH entitled Historical Urban Landscape of Sarajevo, to which the protection measures established by the Law on the Implementation of Decisions of the Commission to Preserve National Monuments, established pursuant to Annex 8 to the General Framework Agreement for Peace in Bosnia and Herzegovina, apply.

Upon reviewing the submitted documentation and the project entitled “Main Design for a Façade Illuminated Advertising Panel“, prepared by the design company „Argentarija“ d.o.o. Sarajevo, and conducting an on-site inspection, the experts of the Institute for the Protection of Monuments were of the opinion that the installation of the illuminated advertisement could be approved in accordance with the submitted documentation.                                                                      

  24. 9. 2025.      Ćemaluša No. 5, Sarajevo

The Institute for the Protection of Monuments was contacted by the Federal Ministry of Physical Planning, which submitted the case file for resolution by the competent authority, in connection with the request of „Svjetlost-štampa“ d.o.o. for the issue of approval for carrying out works for the routine maintenance of the building located at 5 Ćemaluša Street in Sarajevo.

The building in question is located within the boundaries of the national monument „Historical Urban Landscape of Sarajevo“, to which the protection measures established by the Law on the Implementation of Decisions of the Commission to Preserve National Monuments, established pursuant to Annex 8 to the General Framework Agreement for Peace in Bosnia and Herzegovina, apply.

Following a review of the submitted documentation, the “Routine Maintenance Design” prepared by the design company „Arhiplus“  d.o.o. of Mostar, and an inspection of the site, the Institute for the Protection of Monuments provides the following opinion:

The design contains a detailed technical description of the planned works, a bill of quantities and all the necessary graphic documentation for carrying out the planned routine maintenance works relating to the restoration of the façade and final colour treatment, the restoration of the sheet-metal work and roofing, and the restoration of the openings in the building. 

The experts of the Institute for the Protection of Monuments agree with the stated methodology  and material specifications and consider that approval may be granted for the routine maintenance works in question.

The final colour treatment of the building, as well as the type and colour of the vertical and horizontal gutters, must be agreed in advance with the Institute.

The investor is obliged to notify the Institute for the Protection of Monuments of the commencement of the works so that periodic and timely expert supervision of the said works can be carried out, which is the Institute’s statutory obligation. 

  24. 9. 2025    Public Institution Secondary School of Agriculture, Food, Veterinary Medicine and Service Industries, Sarajevo

As part of the regular expert supervision Activities, an inspection was carried out of the façade restoration works at the Sarajevo Public Institution Secondary School of Agriculture, Food, Veterinary Medicine and Service Industries. In addition to the Institute for the Protection of Monuments team, the inspection was attended by the supervising officer and the representative of the works contractor.

It was established that the works were approaching completion. Following a number of organisational disagreements between the investor and the contractor, and at the insistence of the Institute, it was agreed that the scaffolding would be removed during the following week in order to enable a detailed inspection of the quality of the façade works, which was accepted by both the supervising officer and the works contractor.

Trial sandblasting of the building’s stone plinth and part of the roughcast surface was carried out. The results are satisfactory, and it is hoped that, with the approval and funding of the school management, the complete washing of that part of the façade will also be carried out in order to complete the works.

The date of the next meeting was agreed following the removal of part of the scaffolding from the eastern and northern façades.